Project Description
The structure formed by two box girders cut into 22 segments, comprises 1,880 tons of steel components. The complexity of this project is characterized by the high weight of the box girders of up to 91 tons and its tight schedule.
Project Team
Owner:Travaux Publics et Services Gouvernementaux Canada
Structural Engineer: Delcan, a PARSONS Company & DPHV
Project Manager / General Contractor: Pomerleau
Fabricator: Canam-Ponts, division de Groupe Canam
Detailer: Tenca Steel Detailing Inc.
Erector: Montacier