Project Description
The Lee’s Avenue Underpass consists of two rising, curved, trapezoidal girder lines, spanning over an 86.8m opening over Highway 417 in Ottawa. The structure was erected onto off-site temporary shoring. A concrete deck was formed & poured on the erected steel on temporary shoring. Self propelled modular transporters (SPMTs) lifted the poured structure off the temporary shoring and travelled this large structure to its final location during the allotted shut-down time. At 2100 tonnes, the bridge is the heaviest bridge to be erected by rapid replacement over a highway in North America.
Project Team
Owner:OLRT Constructors
Structural Engineer: MMM Group
Project Manager / General Contractor: R.W. Tomlinson Limited
Fabricator: Central Welding & Iron Works
Detailer: Tenca Inc.
Erector: E.S. Fox